So, what can I say about the last week? It definitely didn't go as expected! With time crushing down on us we were very tight and had to prioritise a lot of things before the DMU hand-in. We wanted the level to be fully playable, yet whenever I worked on implementing missing components something else would break, resulting in me having to spent time fixing everything. We were getting close to the end as the week went on, but then the tutor's decided to pull out their final surprise for us: Hand-in requirements!
While we were given a clear brief right at the beginning of the project, this did not include any sort of information on what and how we will be handing in our work. This is always a huge deal with group work, as it has to be clearly visible which person on the team created which part of the final product. In past projects this meant we had to fill in a couple of documents to make this part clear and hand those in together with our work.
For this project, however, the tutors decided to wait until the last 2 days before telling us what we needed to do in order to hand in our work. This included not just a document, but also the creation of a separate scene to show off the work we have contributed towards the group. As you can imagine, this wouldn't quite work with what I personally have done so I had to get in touch with the tutors and ask a bit for advice. In the end the easiest way to show off what I personally have contributed was by creating videos and so once I got home that day I sat down and worked until 4 in the morning on creating videos and writing my document. I didn't fully manage to complete it, even though I spent all night on it, so on the next day I went to labs to finally get it done. This meant that I did lose a whole 2 days that I could've spent improving the level and making sure everything works. In the end I still got back to the level and did some more fixes, however all in all while the level might work now (I say might, because it has a tendency to show some bugs), I am not fully happy with the state it was in for the hand-in.
While the end state might not be that satisfactory to me, the process of getting there was by far the best out of all the group projects this year, but let's round this whole project up with a final post-mortem.
Alice OTM Post-Mortem
To start off, here is a quick summary of the brief: We were given 3 different topics to base our idea on: 'Oxford, Underground and Gardens'. For each of these topics we were provided with resource materials, such as sounds, maps and information/text. The task was to create an interactive level using those resources and sticking to our chosen topic. We decided to choose 'Gardens'.
The duration of the project was originally 10 weeks, with addition of the Easter holidays (3 weeks). However, we were given an extra week, bringing the total duration of the project to 14 weeks.
There is a couple of things that went really well with this project. In particular I am happy to say that for once during this year I had a group project that didn't fully end in disaster. We worked very well together as a team and established a rule right at the beginning to not take any feedback on work personally, which allowed us to give constructive criticism without the fear or upsetting one another. Time management was a big issue in the past and while with this project I feel as if we could've still done a better job, it was actually quite good. We usually spent our time working together in the labs, which saved us from having to organise regular meetings to know what everyone was doing. In addition this also allowed us to distribute work more evenly and easily between each other.
Another thing which really stood out to me was the productivity levels right at the beginning of the project. Within just a couple of days we already had a blockout of our level done and within just a week we already started to slowly populate the level with assets. All while doing concepts on the side. This was great, since during the past group projects our team had spent far too long on creating concepts and only started creating assets way too late.
However, there is also quite a few things that went wrong. While our teamwork was mostly outstanding and I enjoyed being part of such a fantastic team, there was one thing that I just couldn't quite forget about: Team Leadership. As with previous projects, there was no clear leader for the group and while there were 1-2 standout group members who sort of acted as leaders a couple of times, there just wasn't the ultimate leader who was able to take the project where it needed to go. Now this is a point that people can argue about and while our team did function quite well without a assigned leader I still feel as though it could've really needed one. However, this is more of a problem with the fact that we are all students, rather than it is a problem with this project. Since everybody needs to work on developing their skills it would be hard to have one person just focus on leading the team, therefore I don't think there is much that could've been done about this.
Going back to time management there also was a couple of issues that annoyed me. Number one was the fact that I ultimately wasn't given enough time to do what I wanted to do, however this is partly my own fault for underestimating the time I would need to get everything done. I didn't get full access to the level to create the many scripts that I needed to create until very late in the project and this meant that while I did get most things done, it wasn't to the standard that I had hoped and it was riddled with bugs, leaving me to fix those bugs within the last week, which obviously turned out to be a problem due to the documentation getting into my way.
We also had a problem with planning. Since we jumped straight into creating everything, from concepts to assets, we completely forgot about creating an actual asset list. This hadn't been created until a few weeks into the project and even then was still quite vague and missing many assets that we ended up having to add in later.
There was a big change within the project about half-way through, when UE 4.7 had been released. We previously had problems in UE 4.6, since our level was mostly foliage and Unreal at that point didn't have any real foliage shaders, meaning we had to try and fake them, which wasn't ideal and didn't look too great. When the engine update got released we were happy to see that one of the major new features was an entirely new foliage shader and this had helped us a lot, so we immediately updated our level to the newer version. This was a risky move, since updating a game engine in the middle of the project can usually cause a lot of things to break, but luckily for us it seemed to be fine.
Another big change was when I decided to change how the level was being loaded. There is currently 2 ways in unreal of loading different levels: One being the usual load level, which causes the game to stop running until the new level was loaded and two being streaming, which involves quickly 'streaming' in each asset within the level, which allows for faster loading times and gives the level the ability to continue running while the level is being loaded. We originally used the traditional load level, which had caused a bit of issues, so I decided to switch it to be streaming instead, however this meant that there was now a new way of working with the engine, since all of our levels would basically be merged into 1 massive level. This later on turned out to be a bit of a problem, since working within the streaming level would cause a lot of issues, especially with foliage and landscape, which would end up crashing the engine. After we discovered this we had to resort to loading in the levels separately in the editor to avoid these crashes.
All in all, however the project did go quite well compared to previous groups projects. So while I wouldn't do a lot of things differently there is one thing that I would definitely change: Start scripting earlier!
I spent a lot of time at the start just coming up with ideas for puzzles and how I would make the whole level playable, but not actually spent time creating these scripts. They were just lose ideas that I had floating in my head and while most of the time I had some sort of idea of how I would create certain scripts, when it finally came to actually making them, I always encountered some problems. Partially this whole workflow was caused by me not having access to the assets that I needed in order for the scripts to work, for example when creating the fountain puzzle I had to make sure that I actually have the fountain itself so that I could create the puzzle accordingly. However, with some of the scripts I could've probably done most of the work earlier on and then just replaced placeholders later on and changed the script in case it needed changing.
Another thing I would probably do differently is spend more time on creating assets. I like 3D modelling and I am a bit sad that I didn't get to do it much during this project. While I love the unreal engine 4 blueprint system, this is not something that will secure me a job later on and I really want to focus a bit more on modelling, since this is something creative that I feel like I can actually do and is something that will help me in the future, since while I plan on specialising in technical art, I also want to keep my options open and I am always keeping an eye on environment art.
Finally, I am happy to say that we finally did it! The level is playable and looks great; something I could've only hoped for during the last couple of projects. I am glad that we got it over with and frankly I do not really want to look at it anymore, however there is still work to be done and if want to submit our project to the OTM competition we need to keep on working. For now though, I am just happy that it's gone. It was a very stressful couple of months and we all did our best and pushed on until the very end.
To end this post-mortem I would like to share with you the final result of all our hard work:
A massive well done to the rest of my team at this point. Make sure to check out their blogs here:
Denise: http://denisecjj.blogspot.co.uk/
Stay tuned~